Meeting Minute with KPKT on 28th February 2011 // Target Completion Date: 1st February 2012

Dear all,

Please find attached meeting minute on 28th February 2011.

Download below:

FH – Minute 28FEB2011

Cheers,

Vincent

165 Responses so far »

  1. 1

    khairul said,

    Recently (12/4/2011), I went to Condo site and found out as below

    1. Working progress very slow
    2. Nor many workers are there in site
    3. Not sure the building can be completed in time (1/2/2011)..

    Hope commitee can follow up with FH & Kamuja..

    TQ

    • 2

      Munte said,

      If im not mistaken, now they’re doing internal work..so that, we cant see what they have done inside the site..But, if u there nw, u can see they started to do formwork at Block A

  2. 3

    Christine said,

    Hi Comittees,

    The personnel at the site informed us this project will only able to be completed by mid of 2012 due to less workers, they have another project going on other site. They keep on delay the project as what I can noticed because when we visited the site by early of this year, they promised will complete by August this year but seems like just a joke for us. Please visit them & look into it.

    Thank you.

  3. 5

    bukitpandan said,

    Dear all,

    I shared all the concern on whether the target completion date on 1st February 2011 can be meet? For the contractor, they will emphasize on completion of project which can bring income to them and for our scenario at the moment only 4 banks have approved the top-up request (disbursement still pending).

    The committee is working closely with FH to organize the meeting with remaining banks to ensure the top-up request can be approve.

    Let pray for thing to move soonest.

    Cheers
    Vincent

  4. 7

    TL said,

    Hi, dear committee,

    I hope that FH will monitor closely on the site progress before releasing of progress payment from our top up amount to Kamuja.

    Thank you.

  5. 8

    Broken Heart said,

    Saudara2 sejiran in future,

    Seeloknya progress payment & lain2 fees dibayar hanya setelah projek siap…pihak pemaju langsung tidak rasa bersalah melewat2 kerja2 pembinaan..alasan yg diberi (they have another project going on other site) langsung tak munasabah. Dulunya pihak Mudi Angkasa sekarang ni FH pulak, promise macam2 kat kita tapi realitinya hampeh…nak siapkan middle of 2011..lepas tu early 2012 sekarang ni middle 2012 pulak…nanti2 entah apa pulak yg dijanjikan mereka…duit kita nak macam kilat tapi nak siapkan pembinaan cam kura2…fed up hoiiiii…entah2 sampai aku mampos pun projek ni tak settle2 jugak…huhh

    • 9

      Jess said,

      i never heard about their promise to complete this project middle 2012..as i know, they promise to complete on end january 2012

    • 10

      alice said,

      hye broken heart, u should read comment from Kamil..act, dont just complaint and blaming other parties..what we need to do is, try to find sources to top up sum in order to support FH and get our house next year. If fees and progress payment will paid only after their finished their work, i think the project will keep on delay and we still berputih mata..lets be fair and support in order to help them complete their work.

  6. 11

    Vincent Leong said,

    Dear all,

    Spoken to Elsie earlier and she was in communication with FH and Kamuja on our project status. Works is ongoing smoothly on pool area as well as the remaining 3 floor for Block A.

    Work will progress even faster once Citibank & RHB Bank release the top-up sum and let hold our hand together on smooth work ongoing.

    Hold our breath and frustration here.

    • 12

      Lee said,

      No frustration, but left disappointment & speechless. We’ll sit here & wait, see how good how fast the project can be completed & what FH can actually do now.

  7. 13

    Homeless said,

    Sigh…I pray at least next visit the lift is ready then I can see my unit at high level. Must be completed by now since paint work is almost up to the roof.

  8. 14

    Elsie said,

    For your info every two weeks FH will have meeting with Kamuja at the site office. There are workers at the site working and we committee is arranging a site visit by month of May. Please have faith in FH to complete this project and I really need all your support to let this project keep on moving by finding ways to look for the top-up sum. There are purchasers who even paid the whole lum sum of RM30,700-00 to FH because they want their unit to be completed at the soonest possible. IF the $ is flowing in fast then the project will be completed fast……….well FH is giving 18 months to the contractor to complete this project. As for citibank loan there are some purchasers have already sign their loan documentation at the lawyer office and soon the to-up loan sum will be release soon……GOD is there to oversee the whole project and I believe HE knows the pain and suffering that most of you have gone through but never give up….trust in HIM and everything will be ok …….KEEP ON PRAYING……

    • 15

      kamil said,

      Dear all,
      My father is one of the victim here…our family had accepted our `fate’ and thought of moving on with our lives (nasi dah jadi bubur).But alhamdulillah God is merciful..FH has came into picture with a revival scheme, which brings back hope to our family,particularly my poor old dad.We are trying to be as positive as we can and hope to get our completed unit as promised soon.In the mean time ,i think we should do our best to push the banks to disburse the top-up sum to FH, for those not eligible for the top-up sum..probably should try to find other means to pay…we are all worried…what if we kena tipu again…but not doing anything pun we wont get our unit.So the faster we pay the top up sum,i believe FH will be able to push for the work and completion.Lets work together with FH for the succes of this project.I dont think the contractor delay work just because they have other project (sounds a bit ridiculous,isnt it)…everything is about money.Lets be fair to FH and Kamuja…(i’m trying to be positive here..positive energy..).

      • 16

        alice said,

        yeah!im totally agreed with kamil..
        let us try to find and push bank in order to help us to get our top up sum to FH, and let Kamuja doing their work at site..i believe that Kamuja will be able to finish the project on track

  9. 17

    Suresh said,

    Dear all,

    I am sure all of you are still in a puzzle whether the project is progressing and can be completed as per plan. Perhaps my explanation below will clear some of your doubts.

    We on the committee’s side have been in constant communication with FH on the progress of the project. We have requested FH to allow us to visit the project site to see the progress. They have agreed for it and the date is tentatively scheduled to be on the 2nd week of May. But this round is going to be only the committee members strictly.

    The contractor is suppose the complete the project by Feb 2012. If he fails to complete by then, he has to pay a penalty to FH for the delay. I am sure he doesn’t want things to go to that extend. FH holds meeting with the contractor in the project site every 2 weeks to monitor the work progress.

    On the top-up loan matter, Elsie has been liasing with the Citibank officer to speed up the entire process. We believe that Citibank would be releasing the fund soon. In the meantime, the response from the buyers who choose to top up using their own money is overwhelming. So far FH has collected from more than 80 purchasers.

    The rest of the major end-financiers namely, RHB and Ambank are also in the final stage of processing the application. Situation is still under control and buyers need not worry so much unnecessarily. Do remember that the committee members are also fellow buyers like all of you. We certainly would not want to give any false information down here.

    On the other hand KPKT is also closely monitoring the progress of the project. So now its for us to decide whether we want to choose to wait and see or join hands together to help the contractor and FH to complete the project as per plan.

    If you prefer to hear from FH directly on the status of the project, you may by all means call FH at 03-2273 6227 and look for Ms. Yi Wen or Mr. Kumar. Thats all for now.

    Thank you.

  10. 18

    Elsie said,

    Dear All,
    Please continue to be positive towards this project. We are always praying that this project will be completed on time. For those of you who had voted for the scheme to top-up please find your ways for the fund. As you are aware during the voting meeting the contractor did mentioned that ” Ada duit projek boleh jalan tak ada duit projek mana boleh jalan” ! Every payment released to the contractor will certified and checked by FH before releasing it . Talam is no more in the picture of thiis project and please move on with this plan which this project will be completed soon. Our property has increased in value because it is located at popular demand location plus with covered car parks and low density. As you are aware that the Monte Bayu Condo and Glen-view Condo that the value of this property has gone up to200K ++ (location of this 2 condo is very near to our project site) Well I respect every purchasers opinion, suggestion and decision but if we put our hands together for the top-up sum , I foresee we will be getting our keys to our condo soon……………….Please take note our condo (1) 1 km Pantai Cheras Medical Centre (2) 4 km to Jusco Maluri (3) 3 km to Leisure Mall (4) 1.5 km to primary and secondary schools (5) 3 km to Sedaya college (6) Middle Ring Road 1 km and etc……………

  11. 19

    Goh Hock Bee said,

    Thanks to the all committee member who are helping us to follow up the project ! Everyone needs to be positive now. I really want my unit badly and so do everyone here.

    Cheer !

  12. 20

    Hoe said,

    Hi Suresh / Elsie,

    Thanks for the updates and efforts. Two question here :-

    1). Will FH allocate the penalty fund back to all purchasers after FH collected from contractor when they delay the project even one single month or even a day ? How much percentage of penalty FH will charge to the contractor please and are they calculate by daily ? Please stated clearly.

    2). As promised, project complete by Feb 2012, otherwise FH will penalty contractor. Does everyone aware of the meaning of ‘completed’ here ? In generally, project completed means we are getting our key by Feb 2012 instead of only the condo itself being completed but we still have to wait for few more months to get the key which may due to delay of CF & etc. In this case, are we still getting any compensate or FH can penalty related party when the key is NOT passing to us by FEB 2012 please ? We are all being so kind for not ask a single cents from previous developer. What if all purchasers pay up the top up and yet project still in delay progress, for fare we should ask back some compensate this time.

    What you guys think ?

    Need your prompt comments here.
    Thank you.

  13. 21

    khairul said,

    Anybody went to Project site?..How is progress…pls share..

  14. 22

    edwin said,

    Hello committee,

    Can you please update us if you have done the site visit. We were told in this blog that FH has arrange for a site visit but only for the commitee.

    I went there last week and cannot see anything from outside. It was a Saturday and the workers staying there shut the main entrace door when they see me hanging around shooting pictures.

  15. 23

    kae el said,

    Dear all,
    Has anyone ‘liked’ this blog? I think this is a good platform for all of us to share news, be it good or bad. I don’t know about other abandoned projects but I feel kind of close to my friends my future neighbours after going through this unfortunate situation. Our mutual support and comforting words really made this situation bearable. The one thing that makes this perfect would be the keys to our units. Let’s keep this ‘positive thinking’ going and hopefully will be true neighbours by dd/mm/2012. Long live BPNM web blog! TQVM committee for the good work done.

  16. 24

    Suresh said,

    Dear all,

    Just a quick update on the site visit. The site visit tentatively planned to be on the 2nd week of May has been deferred to somewhere in June. Date to be advised later.

    Thanks.

  17. 25

    Broken Heart said,

    Suresh,
    U mean somewhere in June 2011 or June 2012??..orrr June 2013 ..hehehe..just joking from me whose failed to commit monthly payment to bank loan since last 2 years. Might be we will be neighbour in the heaven…yen na dey

  18. 26

    Ms Ng said,

    Hi,

    May I know if anyone has managed to get their loan approved by Citibank?

    I just received an email from FH that they are expecting the top up payment to be paid latest by 18 June 2011, else a penalty will be imposed.

    Please share. Thanks

  19. 27

    Hoe said,

    Hi Ms Ng,

    I am one of the purchaser, would like to know how you managed to get info via e-mail from FH & who are you contacting with please ? As I am not staying in KL anymore and hardly for me to get all the mailing letter from FH, I wish to be direct contact by FH thru e-mail instead if possible for any latest info.

    Thanks in advance for sharing the e-mail address here.

  20. 28

    confucian6a said,

    hi Hoe,

    Please contact with Mr Kumar or Ms Ngi Wen from FH at :-

    Ferrier Hodgson MH 22-M, Monteiro & Heng Chambers
    Jalan Tun Sambanthan 3
    Kuala Lumpur 50470

    P: +603 2273 6227
    F: +603 2273 7503

    Please call them as soon as possible and they shall assist you on how to change your correspondent details…

  21. 30

    Casey Yong said,

    is the visit to the site in JUNE still on?

  22. 31

    KKChong said,

    Dear All,

    Is there any further status for the site? As i know, my bank will going to release the top-up loan soon.
    Worry the porject delay again.

    Kindly please do update further information here to share with others.

    Thank You

  23. 32

    Broken Heart said,

    Dear Casey Yong,
    Site visit to your purchasing unit still on as stated as reply by Suresh. But the date is slighly change to June 2012.

    TQ.

  24. 33

    khairul said,

    Hi Suresh ..

    Pls response..

  25. 34

    buyer said,

    nampak macam tak jalan jer projek nie?

  26. 35

    khairul said,

    Any progress? Pls update..dah lama senyap jea..????

  27. 36

    dissappointed buyer said,

    What’s happening? Have they stop constructing? W’ll like to know the progress?

    Will you please give us the update, Ferrier Hodgson?

  28. 37

    Broken Heart said,

    Dear Dissapointed buyer,
    I just made call to FH regarding to the contruction progress. The FH staff said that they have monetory problem . Other purchaser & u need to topup extra amount around 50k plus the 37k u paid previously. The project will continue after they get enough fund. If everything fine, we will get out dream unit around year 2020…hihihihi…just joking from the frustrated buyer.

  29. 38

    Vincent Leong said,

    Fellow purchaser,

    Whenever comment / input are posted into the blog, please identify yourself instead of merely your nickname. We should be proud of our identify unless you have any hidden agenda. Yes, the construction was on slow pace currently which mainly due to fund from CITIBANK and RHB not release yet ( expected by August 2011).

    For those unable to secure loan for the Top-Up Sum, please approach Ferrier Hodgson and they will try to assist further. Bank Negara has came up with recommendation to all banks to approve the Top-Up Sum (this still subject to individual credit record).

    Do feel free to contact Ferrier Hodgson / Elsie as and when you are in doubt of the construction process.

    Cheers,
    Vincent Leong

  30. 39

    Elsie said,

    Dear Broken Heart,

    I understand and I know how angry and frustration you are because myself also a victim of this project. All of us are on TITANIC and of course we do not want our TITANIC to sink. Well please let me know who you have spoken to during your conversation with FH regarding the to-up sum and completion date. As far as this project is concern everything is moving well but slow as mentioned by Vincent Leong above. To complete an abandon project like this is not easy for FH and the Contractor because they got to look at every point of this project. But I have faith in them to complete this project. If any one of you having problem for the to-up sum from your end-financier please feel free to contact FH. For your information I have being following this project very closely with FH, Citibank and etc………because I want to do my best for all of you purchasers and also I have paid my full to-up sum and I am trusting and believing and praying I will get my key soon………….

  31. 40

    Sow Chan said,

    Dear All,
    Thanks Elsie and Vincent for your clarification. For those who want to make the joke, please dun go thru this blog, I am seriouly and closely getting the info from this blog, please…..

  32. 41

    buyer said,

    I just nak tanya boleh ker project nie complete pada 01/02/2011?

  33. 42

    buyer said,

    typo errror ………….. 01/02/2012

  34. 43

    Vincent Leong said,

    Hi Buyer,

    Which unit do you own? Let FH advise further on the completion as they will gather contractor and relevant party involved for site update soon.

    Finger cross we will get our longunit soon.

    Cheers,
    Vincent Leong

  35. 44

    Casey Yong said,

    I have called Citibank today & they confirmed have released rm30,700 to developer on 29/7

  36. 45

    buyer said,

    Semalam saya pergi site visit di condo kita…. nampak ramai jugak pekerja2 sedang berkerja di site…..harap2 semua berjalan dengan lancar dan condo dapat disiapkan mengikut jadualnya.

  37. 46

    Vincent Leong said,

    Hi Buyer,

    Terima kasih di atas update, committee akan updatekan perbincangan dengan FH yang diadakan pads Sabtu lepas.

    Vincent Leong

  38. 47

    buyer said,

    Hi Vincent.

    ya.. hope our committee can update recent discussion with FH in this blog and hope there is a positive output from the discussion.

    tqvm

  39. 48

    khairul said,

    Yes, recently i went to condo site..Happy to say there are many workers there..Hope we will get our condo follow the schedule on Feb 2012..

  40. 49

    redza said,

    syukur…ambank has released my additional loan to FH…hopefully semua jalan lancar….but hutang bertambah…mudah2an projek berjaya disiapkan february…jika tidak hutang akan bertambah2

  41. 50

    Vincent Leong said,

    Hi Redza,

    What I’m doing now is withdrawal from EPF Account 2 on yearly basic to reduce the loan amount. In additional, I have also withdrawn the whole balance in EPF Account 2 to reduce the loan 2 yrs ago.

    Cheers,
    Vincent Leong

  42. 51

    Elsie said,

    Dear All,
    First of all, Selamat Berpuasa to all my muslim friends.Here are the updates of the site visit and meeting on 30th July 2011:-
    (1) Rooftop of Block B 90% completed;
    (2) Structure work will be completed by end of August 2011 for Block A;
    (3) From the pool side view there is still one more floor to be up for Block A;
    (3) Pool side partition is mostly done;
    (4) Once the structure work is all done; the partition and plastering work will be moving very fast;
    (5) Completion of this project will be february 2012 if everything is moving well………pray hard…..
    (6) Citibank has already release the to-up sum to FH;
    Well, I foresee we will be getting our keys soon if everyone of us do our part for the to-up sum………We need team work……GOD BLESS!

  43. 52

    buyer said,

    Dear Elsee.

    Tq for updating us…glad to here the working is on progress. hope all in order and we will get our condo key by this feb 2012.

  44. 53

    Wong said,

    Hi,Vincent,

    Can i know how to withdraw EPF on account 2 ? What is the procedure and what shd i do at EPF & bank to reduce the loan ? Thank you.

  45. 54

    Sow Chan said,

    Dear All,
    I received the next progressive payment from FH to bank, another 10% for Stage 6 – Internal & External Plastering. The due date is over and bank yet to process the payment. I believe bank also need sometime to verify as this project has been abondon for so long. I will request for the waiver of the panalty if FH ask for it later.

  46. 55

    Vincent Leong said,

    Hi Wong,

    FYI, you may withdraw all your EPF Account 2 to reduce the housing loan with subsequent withdrawal permitted once a year. To start, please approach your bank and have them to prepare the Housing Loan Outstanding Statement as per EPF format (bank should know the format or visit EPF website for guideline. Then you need to visit nearest EPF branch for submission and bring along the Original S & P Agreement, IC and Housing Loan Outstanding Statement.

    EPF will take approximately 1 week to process and they will credit directly into your housing loan account.

    All the best.

    Cheers,
    Vincent Leong

  47. 57

    azril isha said,

    HI

    any idea whether MBB agreed on the top up?

  48. 58

    exnusa said,

    Hi everybody,

    Not to be busybody, but few years ago I Plan to buy this condo. But then I change my mind and get myself a condo at Monte Bayu above nusa mewah.
    Everyday I keep watching nusa condo and wondering when it will complete. From my view seem the contractor will be complete soon.

    Just wondering if you all interested to see the latest development of your condo please drop a email, as i have few picture of your condo from my balcony. I know how happy your all when your dream house will be finished.

    From my view.
    1. Second building is complete almost top floor.
    2. Seem worker start plastering inside house.
    3. Worker is concentrate 1 area at a time so the task will be faster.

    My hope goes to you all…Best of luck….

    cuepacs2%gm4il.com

    change % to alias and 4 as a.

  49. 59

    Vincent Leong said,

    Hi exnusa,

    Thanks for your updates and would appreciate if you can e-mail me the photos for my onwards update into the blog.

    P/S: Trust you enjoying nice view from your unit @ Monte Bayu

    Cheers
    Vincent Leong

  50. 60

    Hoe said,

    Hello Exnusa,

    So glad to know the great progress thru you ! I just managed to paid my top up in full amount with my own saving last month without getting any loan from bank & I really really hope they can get their job done as scheduled. I myself not staying in KL anymore so hardly for me to check on their status. Hope that I can hear from you again soon on their progress when you have time. Really appreciated !!

    P.S : You made a good & smart choice for choosing the condo that you are staying now !! All the best to you & your family :)

  51. 62

    jeffri said,

    Hi suresh/ elsie,
    Can i now whether MBB agreed on the top amount.

    Please update.

    tq

  52. 63

    Vincent Leong said,

    Hi Jeffri,

    It will be best to contact your loan branch to check on the status or alternatively Maybank HQ for status.

    Cheers,
    Vincent

  53. 64

    Exnusa said,

    Hi all..

    Sorry for delay regarding the pictures..Below are the link..
    Day by day pictures…

    http://i902.photobucket.com/albums/ac230/lalusana/sep9.jpg
    http://i902.photobucket.com/albums/ac230/lalusana/sep8.jpg
    http://i902.photobucket.com/albums/ac230/lalusana/sep7.jpg
    http://i902.photobucket.com/albums/ac230/lalusana/sep6.jpg
    http://i902.photobucket.com/albums/ac230/lalusana/june21.jpg

    Vincent… send me your email for me to upload next time.

    p.s sorry for bad quality pictures… my current phone cam drop at monte bayu swimming pool…

    No cam for time being

  54. 65

    Vincent leong said,

    Dear fellow purchasers,

    I received an important yet shocking registered letter from FH, a final reminder to pay for Top-Up Sum by 27th September 2011 otherwise they will cancelled the S & P Agreement and we will become unsecure creditors.

    For those who have yet pay, let work out something urgent as the deadline was due in a week time.

    Vincent Leong

  55. 66

    Chin said,

    I received the same letter, have called them (FH and Bank) to find out. The FEELING i get is this, FH is not enthusiastically helping us to get the additional loan, they are more to finding ways to make us losing our unit, so that they can make more profit selling our unit at market price later. No company in this world would do anything that do not give them profit at all, else we should not be paying top up…

    This is the only thing that i am glad if someone can convince me that i am D*** wrong. Once in a while sending out letter such as this is disappointing, it is not us the house buyer not doing anything, it is them (FH and bank) who are not being “helpful” enough.

    I’m saying this because I’ve already been following every instruction that the Scheme of Arrangement needed, already got approve for top up loan, already do this and that.. still.. this letter came to me.. saying i didn’t want to pay anything..

    Frustration, YES! Disappointed, YES! but what to do? We are nothing more like meat on the table..

  56. 67

    Vincent Leong said,

    Hi Chin,

    I shared your feeling when I saw the letter, well too late. What I have done now are pressuring my bank (Public Bank) to expedite the approval meanwhile I have also faxed to FH to update them on my status.

    You may call Jason of FH to update your status.

    Cheers,
    Vincent

  57. 68

    Lai Fun & Lai Ling A-11-03 & B-10-20 said,

    Hi, all friendly purchaser,

    I am unit of Block B-10-20, have any top-up loan from RHB i submitted the loan application 2 times the bank no information to me. and only photostate the documents please inform any help of the other Bank.
    All for those not yet appprove the loan please contact together apply again. Best regards.

  58. 69

    Vincent Leong said,

    Hi Lai,

    Do call Jason @ FH to find out who is the PIC at RHB HQ then call them urgently for your top-up loan status.

    It will be rather too late to reapply from another bank now.

    Cheers,
    Vincent

  59. 70

    Goh Hock Bee said,

    today I went to the site, so happy to see the workers working on it. hopefully we can get our unit as promised by them. I did took some motion picture to share in this page but cant find the button to share it.

  60. 71

    redza said,

    AmBank has approved my top up loan…but due to some technical problem…the disbursement will be delayed as only 96% of top up amount approved by the bank….i have to pay about RM1.5k to FH and with the receipt Ambank will disburse the remaining top up amount…..

    Really shocked and disappointed when Ambank’s lawyer informed me that FH will start to impose 10% daily interest on the remaining top up effective on 27 September 2011 to me due to the delay in the disbursement of the top up amount….

    What is this peng aniayaan to the purchaser….we already committed to ensure the project will be continued….and some delay should be expected with the current economic situation….

    If they charge me 10% daily interest on my remaining top up…what will be the rest of the purchasers who unable to prepare or ready to pay the top up amount?

    So now the purchaser have to serve their current loan….plus top up plus 10% daily interest due to the delay….

    Can the committee submit an appeal on this situation…at least to assist purchasers who are committed to ensure readiness of the top up and some delay cannot be avoided due to unexpected event….

    really need committee assistance on this matter.

  61. 72

    Hamidah J said,

    How about if FH failed to complete the constuction on Feb 2012?. Did they also been penalty for the late delavery?..anybody can answer it for me… I’m still can’t forget what William (ex- Mudi Angkasa rep) said around 2006 ” u jangan risau le..nanti u dpt semula u punya late delivery charge”…

  62. 73

    Boon said,

    Hamidah J

    I think you still don’t understand the agreement that was signed once you agreed to proceed with the revival of the project. I suggest you go through the contracts line by line. You will find the answers that you had asked. Promises mean nothing. All that matters are the contract.

    There are those who “promote” or I would say influence all the buyers to proceed with the revival scheme as it is and I hold them responsible.

    tq

  63. 74

    Hamidah J said,

    Boon,
    Thank’s lot..I’m know nothing about legality. I also not signed any aggrement because never received the new contract document as u said. However, i still commit to release the top up amount after i spoke with FH rep previously early this year. Can u help me to explain ‘meaning’ that u understand with the containing of the agrrement.

    Besides that, i hope FH/the purchaser commity can list out the list of purchaser that already made the top up amount to ensure FH keep proper record & as our reference. I made the payment but until now, i never received any letter from FH to confirm that they recorded the transaction.

    TQ.

  64. 75

    Vincent Leong said,

    Hi Hamidah,

    Noted that you have paid for the top-up sum as required, great co-operation. Do get in touch with Ms Yvonne of FH to request for your payment receipt.

    Cheers,
    Vincent

  65. 76

    zack said,

    anybody know how to culculate the interest FH will charge us?

    • 77

      Chin said,

      Hi Zack,
      Forget about calculating the interest, you better check with them the cut off date, as the letter i received recently, they said according to the scheme we agreed, if we don’t pay at certain time, they will just take our unit, then we will become unsecure creditor (if i’m not mistaken). That means you unit will be sold by them..

      Chin

      • 78

        zack said,

        Oh my, will they do that…seem this going to be a very long story, cause the bank say they also have the rights to the house….

  66. 79

    Broken Heart said,

    Dear Zack & Chin,

    We are mentimun..Developer & Banks are durian opps mistake like ‘penyamun’..ermm…Just like Chin said, FH will take your unit if u can’t paid the top up amount…Bank still want their money back ‘from u’ every RM including the interest that they already release to developer..Don’t know either the ‘new developer’ will give back the money or not. I believe if they return back the money, they will use certain formula to benefit their side..and we as usual be the victim…ermm…

    The unit gone with the wind. Blacklist titile in CCRIS for sure if u don’t pay back to the bank , worse cases we get ‘bancrupcy’ title.

    Welcome to the Club.

  67. 80

    edwin said,

    dear all future neighbors,

    dissapointed to hear about FH charging 10% interest. i hope for those who got the loan approved, pls prepare evidence that the bank are actually delaying the top-up loan and not you.

    on the positive side, we can see steady progress of construction. this means money is flowing into the developer pocket. i have the following assumption, hopefully someone knowledgable can confirm this:-

    now contruction progresses from the stage where talam stops. example: talam stop at stage 6 in 2006 but now FH complete stage 7. will our bank release money for completing stage 7? i am referring to the money we originally loan from the bank (not the top-up). if i am correct, then we have a good chance the condo will complete soon because money from our original loan will keep coming in to fund the construction.

    i am not saying we should stop paying the top-up, but at least more purchasers will feel confident to pay the 30k when seeing good progress. the bank will also be confident to approve the top-up.

  68. 81

    Vincent Leong said,

    Hi Edwin,

    Bank will release remaining loan as per the stage done, pending that FH will utilize the top up sum for pay the contractor. I myself paid the 10% of the penalty and I guess that without the penalty I will still have my sweet time to work out the top up sum.

    To be fair, everyone will have to play a part to ensure we get our project by mid 2012. Once the CF are obtain, then we can approach any bank to refinance the property and pay off whatever loan taken for top up some.

    Cheers,
    Vincent

  69. 82

    Justin said,

    Don’t play with fire. Are you sure that FH will allow us to pay the 10% interest and take our sweet time to settle the top-up sum?

    As you know, this project has no money and they have already sent out the letter informing who did not pay-up, their S&P will be cancelled and become unsecured creditors.

    It is only safe if you check with FH before it is too late to find out that your unit is gone.

    I thought the project can be completed by Feb 2012? It is so frustrating to hear about the delay.

    Best regards,
    Justin

  70. 83

    Vincent Leong said,

    Hi Justin,

    Yes, FH might allow extension with interest charge for those who can commit on payment timeline otherwise they will proceed with action as stated in the letter.

    Do visit the site for update on the progress.

    Cheers,
    Vincent

  71. 84

    mama said,

    I agree the developer & bank is the ultimate penyamun. & our government do nothing about this. In our situation, the original loan have not utilised fully. there are balance of 30% to be released to the developer but when we applied for top – up loan, the bank of course will not grant u 100% loan. Why on earth they did not release the balance of 30% to the new developer ? the worse the bank ask the purchaser to fork out the money to pay the balance of RM1000 to mudi angkasa & show them the proof then only they will release the top-up amount to mudi angkasa.
    This project really kikis our money.

    What is our right if the project delay again??????????????

  72. 85

    mama said,

    I am very positive about rehabilating our condo.. as our pocket and bank account go thinner to ‘bela’ the condo. We serve the interest monthly ,hv applied for top up sum with additional interest..with all the hassle and problems…+ pray to god that everything to go as plan.

    sincerely, please ask FH what is our right if they fail to complete the project on time??

  73. 86

    kae el said,

    Dear Government Loan purchasers,

    If you haven’t paid up the top up sum, and would like to apeal to the Treasury Department to help out with the tope up sum please be informed that there will be a meeting with them at the following time and place:

    Date: 19/10/2011 (Wednesday)
    Place: Bahagian Pinjaman Perumahan, Putra Jaya
    Time: 10.00 a.m

    For further information please contact Cik Rose (016-6655042). Sorry that this information seems to come a bit late but it’s still a glimmer of hope for those who have a problem with paying the top up sum. Let’s do our bit to get this project completed.

    Thank you and with regards.

    • 87

      kae el said,

      Sorry about the incomplete address. The details of the address are as follows:

      Place:
      Bilik Perbincangan
      Bahagian Pemulihan Projek Terbengkalai
      Jabatan Perumahan Negara
      Kementerian Perumahan dan Kerajaan Tempatan
      Aras 32, No.51
      Persiaran Perdana, Presint 4
      62100 Putrajaya

  74. 88

    Leong said,

    Hi All,

    Just to share my feeling on the site construction progress.

    Actually am almost every weekend to have a visit on the site to monitor the progress since I agreed to proceed the top up.
    Initially the progress made me disappointed and unexpected slow,can say nothing built up from Block A nor outside plaster or painting in Block B.
    On that time,Blk A only build up to 12 floor and still left 3 level to go.This is worry me and do have some negative feedback from others in this blog.
    Now,the condo still look like not complete and under slow construction(if you compare other branded developer construction progress).After I think back about the previous progress compare to now,I just realized that the Blk A already built until level 15 and thereafter is left the top roof to go.Blk B almost complete the roof cover and outside wall painting in the progress.

    My personal point of view,the developer progress is slow but they are delivery.We need positive energy from the developer and committee feedback on the progress.

    Cheers!

  75. 89

    HeadacheJay said,

    Hello Vincent,
    Now u said the project ‘predict’ to complete mid of 2012…from where u get this news??..do u FH crony hah??..what the hell is going on???.. it mean it will delay from the original plan to delever on feb 2012….please la FH, many of us really in suffer now…delay mean we still need to commit sewa rumah for along long time…
    U used the court order to get money from us, but what can we do to ensure u take responsible to delever the project as promised?…
    Please la FH..don’t make we continuing in tense..
    Dear Suresh..do u have any comment?.

  76. 90

    Vincent Leong said,

    HeadacheJay….by all mean e-mail to FH (yvonne@fhmh.com.my / jasonchin@fhmh.com.my / kumarjai@fhmh.com.my) to get the confirmation on completion date on yourself. Labeling me as FH crony is certainly RUDE.

  77. 91

    HeadacheJay said,

    Nusa Mewah Committee,
    Any plan for purchaser to visit the site?..Did any parties responding to monitor the development progress?. I’m admit be emotional in previous comment..appologise me Vincent..

    rgds..headacheJay

  78. 92

    Andis moh said,

    X tau nak ckp apa……………… frust sgt,,, anak dr baby dah menengah………

  79. 93

    edwin said,

    I remember somewhere in this blog one government department agree to monitor this project. Commitee, please confirm if this is correct. If “yes” did the government officer visit the site?
    I also remember there is also a group of people act as “quality control” comprising members from the commitee, FH and relevant government officers. How is that coming along?

  80. 94

    edwin said,

    Hi Elsie,

    You said you worked in a law firm, and agreed to check with your collegue lawyers whether the bank will utilized the money from the original loan still undisbursed. I know that was few months back but please check because there is still a lot of money.

    Look, the 30k top up is not going to last because there are still people not yet paid. The top-up sum is just to start the engine and once the car start to move, you need petrol to sustain the construction momentum.

  81. 95

    Elsie said,

    Dear Edwin,

    For your info now most of the banks/financier are joining in for the top-up sum ever since Bank Negara came into the picture. As for the balance loan sum that are still undisbursed, it will be disburse accordingly to the S&P progress payment schedule. Once the court order is issued we have to comply with it . So if you really want your unit please do so and do your part to settle the to-up sum or contact FH for more information about this. My prayer is soon we will be getting our keys to our condo……….we will I know for sure………….

    • 96

      Edwin said,

      Hi Elsie,

      My top-up sum already approved, had been released to FH and now started paying the monthly installment.

      I am trying to see the big picture because focusing on myself will not achieve everyone’s objective. That’s why I did not mention I have already done my part.

      Based on Suresh and your explanation, my understanding is after a stage is completed as per the S&P, architect will validate the work and upon their satisfaction, the bank will release the undisburse money for that particular stage. Correct me if I am wrong or silent means agreement.

      As of last weekend, Block B have completed with roof covered. Units facing KL already painted while units facing the hill without paint. Block A, construction on 15th floor is on-going with pillars done, no walls yet. Comparing 1 month ago, they progress 2 floors. No bad although not as quick as I would expect in order to meet the June 2012 deadline.

      I will give update regularly since I am staying in Cheras.

  82. 97

    Suresh said,

    Dear all,

    I have been following the comments posted in the blog. Majority of the purchasers are kind of worried on the progress of the construction. To make things clear, the existing committee members are a group of purchasers who volunteered themselves to be part of the pro-tem committee which represents the entire purchasers.

    KPKT is the goverment body which is monitoring the progress of the entire project. KPKT has organized a meeting with all the end financiers and got Bank Negara to give clear direction to all the banks to agree with the scheme. Persuant to that, all the banks have agreed to support the scheme but the approval will be given on case to case basis.

    As for the existing undisbursed amount, the bank can only disburse the sum upon completion of a particular stage stated in the S&P. The reason why we are required to top-up is because, when the project was abandon previously, a lot of metal grills and electrical wires got cut and stolen. On top of that, there were some price increase in the building materials. In order to justify all this costs, the contractor did survey and estimated the total project cost. After minusing the undisbursed amount from the end-financiers, an additional RM11mil is needed to complete the project.

    The breakdown of the RM11mil was clearly stated in the ES report. The ES report was posted to all the purchasers prior to the balloting session. KPKT only stepped in after the court approval was granted. The committee did approach KPKT requesting for some financial aid. But since our project is classified as high cost condo, we were told that the goverment gives more priority to low cost abandon projects. However they agreed to assist us to do the talking with the end-financiers to agree with the scheme.

    Now, some of the banks have already released the top-up sum. Some in the stage of preparing the loan aggreement and some are still in the process of drafting the offer letter. Whatever it is, if you can provide sufficient details to FH that your loan application is in progress and the delay is on the banks side, FH will allow you some extension. But in order to show some committment from the purchaser, they want the purchaser to pay some amount pending the bank approval.

    I suggest those who need further information on the progress of the construction and the status of your loan application to regularly check with FH at 03-2273 6227. You may talk to Yi Wen or Kumar.

    Thanks.

  83. 98

    Justin said,

    Dear Suresh,

    As much as you know, we the purchases are considered part of the financier in this abandon project when the court order was issued. I believe we all have the right to know the progress as well as how much funds was collected and disbursed during the revival construction periiod todate.

    In this way, we know the status how well the project is being carried out and time-taken to complete each stages of the project. FH, please update us and don’t keep us in the dark.

    The project has been taking too much time. So many of us here are struggling for too long. We trust all of those concern and involve in this project to do their part and speed up the completion of the project.

    Have some mercy and help us all. May God Bless you and all.

    Cheers,
    Justin

  84. 99

    TL said,

    Dear All,

    Today I pass-by our condo site, there is activities going on at Block A.
    Block A formwork have reached the roof level but still in progress,there are workers lay bricks at level 14.

    While at Block B the external wall facing the swimming poolside not yet plaster. Carpark block not yet plaster.

    That’s what I able to see from outside the fence.Seem like the site work progress is really slow and unable to complete by Feb 2012. I hope that FH will look into this matter.

    Thank you.

  85. 100

    Chin said,

    Dear All,

    Correct me if i’m wrong, i remember when FH called us for a big meeting with the developer also there, telling us that the appointed developer has passed the standard required by FH, and that they can finish the whole building without the need for us to fork out a single cents. Right?

    I do understand that we must pay the top up and I’ve already got my additional loan and serving 2 loans for my unit now.. Burdensome, i would say, frustrated, definately. But should we not worry about others who have not paid in? Since the developer will still complete it anyway? Let us be more understanding, and show some empathy for those who still struggling to get the additional loan approved.

    Of course, I would not discourage other from getting or paying the top up loan, it is just that i really think it is not necessary for us who have paid the top up, to pressure those who have not paid yet (but are trying very hard to get the loan), and also there is no point passing negative remarks here, we are all in the same boat..

    I’m waiting just like all of you, paying 2 loans and house rental like all others, supporting the family with less than average pay, it would help if we encourage one another, helping one another in these time of need. Is this blog all about??

  86. 101

    redza said,

    Hi…agreed with you mr chin…

    by the way, the rest of the purchasers must do their best arrange for top up or clear the obstacle in getting the top up and remaining financing amount. otherwise they will loss their ownership against the unit…as majority has agreed with continuation of the project.

    with a majority rules, minority must “all out” secure the top up….

    now, i have to serve two loans top up and new financing amount as FH already start to instruct bank to disburse RM14k for tiling (eventhough my unit already tiled during visitation together with Teratai ADUN…..)

    ……from first financing…big worried with development at site…too slow and i dont think by february 2012 we can get our key for the unit….

    committees……appreciate your comments and feedback at new page and not replying this message as its to length to scroll down and read…..

  87. 102

    Broken Heart said,

    Chin,
    Since I’m signed the S&P agreement on 2002, I heard dozens of promise & ‘good news’ either with Mudi Angkasa ( I thought this company was subsidiary of TALAM ) or now with FH. I also attended the meeting with FH and still clearly in my mind with the statement by the FH representor that they will appointed the qualify developer for this suck project. It’s mean, they can completing it without commitment by the purchaser. That what previously FH said but totally different now..project only can be smoothly running if all purchaser settle the top up amount … ermmm..
    Redza,
    I agreed with u that this project can’t be complete on February 2012. With the progress on site, I also fully confident that it still cannot deliver until mids of 2012. Anyone want to bet with me?. Elsie, Alice or FH Director dare you take my challenge?..pthuii..
    Don’t be shock if FH requested another top up amount after all of u poor purchasers resolve/settle these top up cost . They can create dozens of reason to rob your money like they simply will terminate the S&P of the purchaser whose failed to commit.
    To the Mudi Angkasa Board of Directors, if u read my comment, u should know that u already made me suffer & struggle. I just want to say that I’m praying that u dies with the humblest…

    Broken Heart

    • 103

      Lai said,

      Agreed with you Broken Heart, i’m always praying those bastards from Mudi Angkasa or Talam for their 绝子绝孙. Sure they will receive the biggest retribution some day…They must have to pay back. Just sooner or later…

  88. 104

    miss c said,

    hello guys m one of d buyers with d gov loan.went to FH offc yesterday to fully pay. the topping up on 2.12.2011 by using a personal loan.met with Jason who immediately issued a receipt 4 me.wat i been told was dat the project is progressing as schedule.did went to d site to visit……remarks block A progressing up 2 15 storeys without d individual units..block B completed but no fully painted, swimming pool completed n so is d parking lot.i believe d project will no longer b an abandon one …..but 4 sure 2 those who did not response with d due date wll find the s&p being terminated n if sold(by d liquidator) will get back dollar to dollar xcept 4 some fees.sori cant remember…dat was minuted during our meeting with bpp n kpkt….chaired by MR THANA in October 2011(gov loan buyers)

  89. 105

    Eric said,

    Hi Committees,

    As told by Kumar from FH last time,there should be another site visit between developer & committee on Oct/Nov 2011 and will update to the purchaser.
    Can any one from committee update the status?

  90. 106

    Broken Heart said,

    Miss C,

    Yesterday i went to the site for eyewithness of the progress..i still fully confident that they can’t deliver the unit to us by february 2012. Besides that, what suprised me were the big scrach on the wall ‘ GAJI LAMBAT’ ..’Rokok Habis’ and other protes words by the workers there…
    Hope FH make sure that they care their site workers ..

  91. 108

    buyer said,

    apa dah jadi???..

  92. 109

    buyer said,

    apa dah jadi…..the real situation is if money coming in as proposed progressing fast and no money progressing slow..some who got d topping up loan made payments,some who got personal loan made payments,some who couldnt got both …..pity them…..curse those involved with MUDi ANGKASA for their doings causing d mishaps but some who got both but wait n see attitude n giving negative comments what can we say……if any of them attented d meeting with kpkt n made reference 2 FH they know dat bank negara had highlighted our project to all gov n non gov enfinancers….and those who couldnt get d topping r due 2 their personal eligibility……now if u we pay we get d house n if we dont pay we dont get the house.The court order still governs……the only thing to do is wait for the house to be completed fast or slow…..as some wants the house to b completed then only pay eventhough interest will b charged…..those r the scenarios at the moment…….hav u paid ask yourself thats it…..if everyone does it will b ur dream house 2012 …..remember d slogan together we unite …..n together we sink r we all willing to do it……my humble apologies to those who REALLY couldnt and had to let it go. They know dat the house would b resold by the liquidators……i sincerely understood the sorrows n pray with them……there’s always blessings in disguise.

  93. 110

    Broken Heart said,

    Top up & units will be resold by liquidator is another issues..purchasers face suffer also not the developer & my problem…but what i stress & really need to know is the DATE when they should complete this project?..february 2012 ?. June 2012..december 2012, january 2015 or Liquidator still don’t have the date yet.. when it finish it finish laaaa…..Anybody know please answer my question..

    Everybody hate negative responses..but please understand that we alway be feeds with lot of promise but on reality its not…we try to be patient & give commited what ‘the crook’ need..How about the result?..
    Liquidator can give the dateline to purchaser to settle the top up amount..did they also have the dateline to complete it???..

    Might be this is our (puchasers) social obligation for the ghost around Pandan (including Mudi Angkasa Directors) whose don’t have residence..they also rakyat Malaysia…huhh

  94. 111

    Buyer 105 said,

    bersetuju dengan broken heart….bila nak siap?? FH kena kasi satu dateline..

  95. 112

    khalil shariff said,

    i had a problem to obtain top up loan from the bank, pls advise.

  96. 113

    khairul said,

    I tak tau nak cakap la..tapi masa i went there … i saw almost 80 to 90 workers there..but namapak progress still slowwww..external nampak tak banyak berubah…internal tak pasti..

  97. 114

    SARINAH said,

    I have done my site visit on Sunday, 8th Jan 2012. It is impossible to complete the job by end of January 2012. We, as a puchaser have paid RM 30,000 to ensure the job can be continued and as promised to be completed by end of February 2012. What would happen if the developer can’t commit with their promise? Again..and again…the purchasers be a victim. Nobody wanted to know that Nusa Mewah Villa Condominium puchasers was victimised!

  98. 115

    Broken Heart said,

    Dear Sarinah,
    Suprise me that u just today realize that we were the victim…hahaha…who told u that this project will completed by end of february 2012?. Might be u have problem with your eyes..they (the our noble Liquidator) said February 2021 la..huhuhu…delay mean they can ask us another extra cost..delay mean they can ask another court order for top up money from bloddy fool like us and for who don’t want to commit, they can create another exercise to rob the units from u.. If they completed on time, they will lost income…they will lost the opportunity to get easy income…

    The FH,
    As Malaysian, i’m really proud & fully respect yours. Very good strategy in business and can be role model to other Liquidators company in future how to cheat fool purchasers…

    I teach u a tip Sarinah.
    1. tunjukkan awak punya jari ke kepala
    2. then u said ‘ saya bodoh..saya bodoh..saya bodoh’..hihihi

    i’m sure after u practice this 10 time..it will release your tense…

    • 116

      Sow Chan said,

      Hi broken Heart,
      Do you mind to let us know who you are ? which unit you are ? Since you are so aggressive to update us the status, why not you join the committee and help them follow up the status with FH. Putting in real ‘value’ to our house rather than talk so much nonsense in this blog.

  99. 117

    Siti said,

    Hi everyone,

    I’ve been reading all the comments today and I am really shocked. Actually, I am one of the purchaser at block A-2-2 (if I’m not mistaken) and I just came back from my study leaves (not in M’sia). It seems that I’m late or to be precise, the date for me to settle up the top up sum of 30k is already due. However, do FH has the right to take our unit and terminate our S&P? Is this agreed by the bank? Besides our loan is with the bank, not with FH.

    Add to it, from the above discussion/curse/frustration/etc, it make me wonder, is it worth it for me to apply for the top up loan from the bank as most of the comments here had showed that the completion might again be pending. (Especially comments from Broken Heart which he has the point there)

    Seriously make me scared of giving out the top up sum but at the same time I’m also scared that my unit might be sold.

    Pls tell me what should I do!

    • 118

      Chin said,

      Hi Siti,

      Please contact FH as soon as possible, talk to Ms Ng or Mr. Kumar. They will advice you appropriately. Don’t worry, we are all in the same boat.

      • 119

        kae el said,

        Hi Siti,
        I agree totally with Chin. Pls ponder no more and meet up or call FH for the current situation of your unit. Not all are negative feedbacks, we do get positive ones too. So have faith.
        Good Luck and all the best to your unit
        .

  100. 120

    khairul said,

    Broken Heart…jangan macam tu la..saya pun ada pergi lawat our condo ..memang the condo takan siap end of Feb 2012..tapi ramai pekerja masih disana..mereka sedang siapkan tingkat 15 block A
    …Block B pula.. saya lihat tingkap & atap sudah dipasang.. Kalau FH nak tipu..tak payah lah mereka susah – susah nak pasang tingkap & atap..nak buat aper..

    Kalau i tengok progress sekarang…rasanya middle tahun ni rasanya boleh siap..sikit lambat..tapi yang penting siap..So pls be positif..dari tiada harapan langsung..macam u..I rasanya u ni mesti one of purchaser yang tak bayar topup 30K..betul kan???? then terus kacau..bla bla bla…pls respect sikit pada all purchaser yang masih ada menaruh harapan..

    TQ.

  101. 121

    Bonggo said,

    Broken Heart, I know the frustation. But please talk with manners. Jangan cakap biadap dalam blog ini. We’re all going to be neighbors. I know we all got cheated the first time but now the target is to minimise the loss and hope for the best on the project.

  102. 122

    Vincent Leong said,

    Dear all,

    Latest update is FH will sent out letter in February 2012 to update on construction process. Till then please hold your anger and frustration. Those who have challenge or yet to settle the top-up sum, please ensure constant contact with FH.

    Cheers,
    Vincent

    Together we pray for the positive update in the letter.

  103. 123

    Sow Chan said,

    Hi all,
    Agree with Khairul, Banggo, this blog is for us to share the information. I am checking this blog everyday, but really cannot tahan this broken heart, talk lots of nonsense. We still have the hope on this house. If you are not willing to top up tht is your choice. Please do not miss use this blog.

    For all, just to share with u, the value of condo become better, especially the location near to KL town, if you r one of the investor, u should understand, u will get nothing if u dun want to top up, if u take the risk to top up another 30k, end up u may get your house for market value >170K. If u r those purchaser already paid for 70%, the best choice is top up.

  104. 124

    Broken Heart said,

    Dear Sow Chan @ Sow Hai..hehehe;
    Firstly, thousand apologies for making u ‘cannot tahan’ with my preveous comments. 穷人 for me when u be my sister neighbour in future…hehehe…another jokes from me..if u feel my comment is totally nonsense, just ignore it…

    U right Khairul when u said i’m one of the purchases that cannot commit with the 30K.. i also not made any loan payment to bank since 2009..with my salary around 2.5K, i don’t have ability to continueing payed to the project with no direction (on that moment). Because of that, i’m becoming black listing & process to become bankcrupcy on progress…huhuhu

    Besides me, my sister also was one of the purchaser. We plan earlier to leave side by side unit..we dream lot , but IF (iiiffff) this project completed sooooooonnn, i’m only can be the vositor..

    Bonggo,
    What do u mean with ‘cakap biadap’??…Did with said that the Liquidator do not delever what with they said mean ‘cakap biadap’ ya?..

    Ok..i don’t want and don’t like to argue with both of u..i know that all of u also realize that u were the victims just i am..butttttt…

    i. I don’t want my belove sister become another victim like me, face with lots of problem ..with bank..with legality..with wife.

    ii. FH as the liquidator did not deliver like their promise during the early meeting with the purchasers.. I attended the meeting with FH and still clearly in my mind with the statement by the FH representor that they will appointed the qualify developer and fund is not the problem..in fact ??? pthuiii

    iii. U as the puchaser have the dateline on Top up payment…did FH have their date line???…I call Kumar (FH) earlier but he also cannot give me the date with unreasonable explaination…but last time they simply said…we WILL completed this project on February 2012. Did the decicion on completing on that date is legal documented?.deyyy..pooodahhh..for sure it not..Liquidator is enough smart on covering their risk & weaknesses.

    iv. My last question TODAY..hehehe… Did u as the puchaser whose commit 30k extra were covered by Legal?.. What happen to your top up money if FH like Talam/Mudi angkasa cannot complete this project?..

    one mre time sorry & see u again next…hahahehehuhu

    • 125

      Bonggo said,

      Broken Heart, maybe biadap is not the proper word but that sentence was directed when u making ‘saya bodoh’ joke to one of the purchaser. We are all already down, don’t need another ‘negative support’ from fellow purchasers.

      Whatever comment u want to make to FH or Talam – go ahead, thats your voice

  105. 126

    ed said,

    What to do when purchasers are like a meat on the chopping board. The government is not doing enough to protect the purchasers.
    By right government should confiscate all assets of developer, sell them and use the money to fund abandon projects.
    Developers are rich..they have money to hire lawyers to find loop holes in the legal system. If we challenge them using legal system, for sure they will win. People say dont fight with people in their own backyard.

  106. 127

    buyer said,

    miss block b ,
    guys i contacted Elsie to get some progress.She said it will b completed by mid of this year.I also contacted En Amir d contracter,He also mentioned mid, reason being top up payment not being paid as progressed so slow project movement..He said after CNY FH had confirmed that most buyers {gov n non gov loan} had their respective top up loan approved n had d details fr those who terminated their condo….fr there they will proceed as wat is left 2 finish with d cash flowing in.2day i went to the site, block b fully painted in white, block A 15th storey a few individual units to completed b4 putting the roof,Pray hard guys it certainly wont b an abandoned project but bear a bit of d delay due 2 constraints reasons from d buyers who eventually got d top up loan approval n slow but constant project movement which with god willingly we will eventually get our condo.More details contact FH personally ……..

  107. 128

    buyer said,

    miss block b.
    helo sow chan jz want 2 share something with u.i attended a meeting with FH ,En Amir and Mr Thana from kem prmhn @ putrajaya mid of Oct 2011 abt wat governs d court order(gov loan buyers) …..anyway Mr Thana asked abt d value of our condo…b4 completion as it is now RM145K but after completion RM 170 to current market value.Mr Thana advice was pay up if not lose d condo but still retain monthly payment to pinjmn prmhn and r still at loss bcause there’s no more condo @ kl vicinity at that price….pemaju cannot uphold d promises to complete in Feb 2012 …no cash flow.most of us paid up b4 31/12/2011

    • 129

      Sow Chan said,

      hi, thanks for your sharing, is true I believe we can get much more better price if we hold the house abt 2-3 years after completion.

  108. 130

    Broken Heart said,

    U are right Sow Chan/Hai,

    Yess we can get better price when we hold the unit after 2-3 years completion..location nearest to city centre and the grave beside the mosque, u just walking to klcc…If u can hold after 10 years are better dear..huhuhu…completion date ..1 june 2020..sold on 2023 after 3 years..2023 and half purchaser passed away…

    Disgust with statement u made dear..just confort & nice in hearing..but nothing ..uwekkk… u talks nonsense Sow Chan..hehehe

  109. 131

    CJ said,

    i think there is not only 1 broken heart, there r broken heart I, broken heart II, broken heart III…

    i share ur feeling, broken heart.

  110. 132

    IDA PPUM said,

    APA YANG SAYA TAHU..BROKEN HEART TU ADA SAKIT JANTUNG, SEBAB TU DIA TAKUT TAK SEMPAT DUDUK CONDO TU,LAMBAT SGT NAK SIAP..HUTANG PINJAMAN DAH BERTAMBAH…BERTAMBAHLAH SENGSARANYA..KESIAN…

  111. 133

    TL said,

    Hello everybody, since we all knew that our condo cannot complete in february 2012. Can FH give a new completion date?

    • 134

      Vincent Leong said,

      Hi TL,

      As per my message earlier, FH will send out the letter on site progress and completion date by next month.

      Wishing all future neighbor Gong Xi Fa Chai and happy holiday.

      Cheers,
      Vincent

  112. 135

    TL said,

    Hello Vincent,

    Thank you for your info.

    Here I also want to wish you and our future neighbour Gong Xi Fa Cai and Happy Holiday.

  113. 136

    Chin said,

    Dear neighbors,

    Just visited the site, and judging by outer view, the condo definitely cannot be ready in February, but i can see the some progress from my last visit.

    Block A final floor roof thrust is taking shape, and block B looks completed to me. it can be completed this year if everything still moving.

    Cheer up everyone, its gonna be a great year this year !!

  114. 137

    Broken Heart said,

    Dear Vincent (web blog moderator),
    I try to download the minute of meeting between FH & KPKT (28/2/2011 – Stated that Target Completion date 1st Jan 2012). However message ‘file not found’ displayed. I would like ask help from u to attach it back if u still kept the copy. Might be something interesting inside the minute.

    Last night on TV3 news shown frustration protest of Pulau Indah purchasers. I’m imaging of Chin, TL, CJ, SOW CHANN, Binggo & me when i saw the protestors..hihihi. Although I was wide-open, but I realized the fate of all of you are better than them. I hope the committee can close monitor their case. Might be u can get something from them because it look like simular case with us.

    Late but still want to wish Happy New Year (Water Dragon) for all of u. Hopefully u can celeberate it at Bukit Pandan Mewah Condo next year.

    Vannakam

  115. 138

    Broken Heart said,

    Latest news..Shocking to hear that FH will terminate the current contractor because they cannot deliver work as stated in project timeline. Besides that, MPAJ had send ‘warning letter’ to FH because of the contractor employed illegal worker from Africa. FH on process to take legal action to sue this company..

    Besides that, FH request purchaser to be patient because they will replace the contractor with the new one. They promise that it will settle ‘appointed’ of new contractor before december 2012(construction complete don’t know yet) ..ermmm

    hehehe..can’t wait until April to made ‘April Fool’..i made February Fool first…huhuhu…Sow Chan admit that she check this site every day…so u can read something new dear…huhuhu…february fool..february fool

  116. 139

    Jason Lee said,

    Dear all,

    I have just got a reply from person in charge from FH regarding the rumours of the termination of the current contractor :-

    “Must say that we were as ‘shocked’ as you by theshocking news from your blog. Works at site were slow due to the festiveholiday and we didn’t terminate kamuja. We are working on some plansto expedite the construction works.

    For your info, we didn’t receive any warning letter from MPAJand there is certainly no plan to take legal action against the contractor.

    We shall update the purchasers on the site progress once alldetails are finalized. ”

    Hence, dear all purchasers, please stay calm and do not interfere by unnecessary rumours that affect our emotion towards this project.

  117. 140

    Broken Heart said,

    Hi Jason,

    I just made ‘stupid joke’ on comment number 138. Did African came here to be the field labour at contruction site?.. hihihi.. they (the Africans) either came here to involve in drug syndicate or cheating fool local girl…i told u there..that only my February Fool before April fool come..hahaha

    But its ok Jason. Immediate response from u to contact FH for updating the project status was very good…hihihi..i’m appreciate that..others too..

    Response from FH when u highligted the rumours/stupid joke was ‘ We are working on some PLANS to EXPIDITE the construction works’ … i hope u can ask follow up from FH what plans they have to expidite the contruction work and what they mean with expidite the construction..2 weeks, 1 month, 3 months or 1 year???…better give preassure to FH with such questions like that..

    have plans..expidite..have plan..expidite…another promise from FH to the fool purchasers..hihihi..huhuhu…

    I miss comment from Sow Chan..hehehe

  118. 141

    Jason Lee said,

    Thanks for your response Broken Heart, person in charge from FH saying that they will send out a letter for the latest updates of the project by March (early or mid of March).

    If we do not receive any update by March i believe our committee will follow up closely with them.

    Stay tuned. Thanks.

  119. 142

    IDA PPUM said,

    bukan broken heart saja yg respon masalah ini ,semua pembeli nak projek tu siap tahun ni…duit dah top-up 30,000lebih tunggu apa lagi..kami nak pembelaan,perlindungan..tolong lah kami…sampai bila kami nak hutang dgn bank,duduk menyewa..mati mcm ni…

    • 143

      Loyalty Waiting.... said,

      Hi All,

      Hope the property will complet soon. Anything info, hope Commitee can update in this blog for all owner of property wil get the correct info about the status of this project.

      Anyway, please read only the commitee info. If not please direct call FH for the info and please get the name hows was give the info to you.

      Thank you

      Loyalty Waiting….. :)

  120. 144

    Loyalty Waiting said,

    We all are know sufer but after the property completed….hihihihi….will come better and better to your life and all you family…..

    Hope all can pray for this property can be completed….

    Thank you

    Loyalty Waiting…. :)

  121. 145

    pembeli kecewa said,

    tengahari tadi saya pergi ke site tengok tak ada lak pekerja yang sedang bekerja…..kalau macam nie bila nak siap nyer…..FH kena bagi satu dateline bila nak siap kalau tak it is not fair to buyer.Duit tambah RM30,000 pandai pulak bagi dateline kalau tak kena late interest..projek bila nak siap tak ada dateline pulak…adil ker???

  122. 146

    Broken Heart said,

    Pekerja Kamuja tidak bekerja sebab mereka masih lagi dalam mood festival holiday…hahaha

  123. 147

    exhauster said,

    Just called FH this afternoon and informed that the TARGETED completion date will be on END OF 2012.
    I don’t want to write the reason given here as they can give many reasons behind….!!!
    Another delay & delay by their stupid way of project management and reasons..!

  124. 148

    Broken Heart said,

    They already get top up RM from yours..that their target..just wait another top up request from FH after this .. Mudi Angkasa = Talam = FH…no different between them….I lack the suitable sentence to describe this kind of beasts…fools always been cheating..don’t pay top up will loss the units..when u payed..they take oputunity to cheat u again & again..huhh…might be Pandan Mewah Condo born to be a loser…pity yours & me too…

  125. 149

    Broken Heart said,

    Commitee or Sow Chan…i miss your info & comment..don’t be dumb & deaf after top up not already the issues right now… please be responsible

  126. 150

    Broken Heart said,

    To expidite the project????…have plan???…你他妈的 to FH

  127. 151

    khairul said,

    commitee..pls call FH and ask them bila rumah boleh siap? Susah loo macam ni, apa sudah jadi…

  128. 152

    khairul said,

    Baru call FH, Mr Kumar, dia update memang projek ini sekarang memang sangat – sangat slow, tiada cash flow..hanya 50-60 % saja yang bayar topup itupun kebanyakannya tak bayar penuh… ada lebih 100 buyer yang tak bayar langsung.So FH telah terminate S&P mereka iaitu pada Dec 2011. Sekarang FH tengah cari buyer untuk membeli kesemua rumah tersebut. Dia kata ada lima buyer telah hantar proposol, so FH tengah nilai mana yang memberi pulangan setimpal. Buat masa ini, dia kata projek ni dipantau oleh orang Kementerian dan FH selalu sentiasa memberi update kepada mereka. So dia kata jangan risau FH tetap akan menyiapkan projek ini…boleh percaya ke!!!!!

  129. 153

    Hoe said,

    To FH,

    I am one of the purchaser who didn’t able to get loan from bank for the top up. I have no choice but take out all my saving just hope the miracle will happen ! Please don’t dispointed us & pls make it complete within this year ! I believed many of us in deep trouble now with finance & the only hope we have now is you – FH. FYI, I am not going to pay another top up for the second time & I am sure many of us won’t too.

    FH being told that the project will delay from Feb to June 2012 when I tried to ask during Sept last year. Now we are being told that project delay AGAIN & might be complete by end of 2012 but we didn’t get any bonus from the delay and the only thing we got is ‘WAIT’…..we are being too kind to them !! Anybody can tell us what we can do now to get back what we suppose to get asap without waiting anymore ??? We are patient enough to wait for 10 years.

  130. 154

    mama said,

    Ooii..bila mau siap ??? delay delay delay..minta duit tak sempat -sempat, kerja macam siput babi…

  131. 155

    Broken Heart said,

    Dear FP (fools & poors) Pandan Mewah Purchasers,
    Although i’m don’t have ability to commit with this saviour/RESCUER scheme propose by the your hanoured liquidator, i still shared your feeling right now with the current situation that u face with. I never expected that previously joke i made suddenly become a reality.

    I realise that already lost my unit but i fully hopes that this project completed as targeted. Just like i said before, my sister also the purchaser and no big different between she & me..suffer..impact from this sick project.

    Dear commitee..i like to share my opinion here…

    1. u should get project status report from FH & share with the loyal puchasers here by updating periodically in this blog..
    2. u also should get & kept the original copy from FH regarding to the their proposal paper and the court order..this document will useful as the avedence when u need to take futher action in future.
    3. Any decision or minuntes made between FH, KPKT & others related parties also should be properly kept by the comittee.
    4. The project plan & the project timeline should also been keep shared with the purchasers for close monitoring & tracking purpose.
    5. Any issues rises during the execution this project must be log and immediately highligted during your meeting with FH & the related parties.
    6. Commitee & puchasers also have right to know and be inform with what & how FH manage the top up amount they get.

    Besides that, committee also should get the LIST of purchasers whose already commit to lets FH SAVESSSS their property by follow ALL FH requirement & needs..PLEASE attach the list here, so early & immediately action can be made if their name missing from the list.

    Dear appointed commitee..please deliver your role..u will be appreciate not by me but from the FP (fool & poor purchasers).

  132. 156

    khairul said,

    I support what Broken Heart suggested, Commitee please be more active and deliver your role. Pls don’t just senyap jeaaa…where are u now???? Please update the latest info in this blog as what you all know..about FH, about Kamuja, about topup list, about FH plan and bla, bla, bla…pls share

  133. 157

    nicky said,

    FH contact email or person in charge is ??????

  134. 158

    DecadeGeneration said,

    Hello all,

    New completion date given by FH as mentioned by Exhauster will be End of 2012.

    FH do not simply give a completion date to make all of us to feel happy, without any commitment, without any black and white written.
    How can we trust this given date?

    10 more months left for this year 2012. If you (FH) are serious about this date, should inform Kamuja to add more workers, at least 100 workers. Then only can see the progress.

    FH you have a good track of record for handle a lot of abundance projects and able to complete but we are wondering actually you take how long year to do so?

  135. 159

    Suresh said,

    Dear all,

    I just called FH and spoke to Jason. I was told that the workers have stopped work for about 2 weeks now in order to allow the QS team and the consultant to do the evaluation.

    I have explained to them that if there is a change in the completion date, its their responsibility to inform all the purchasers in writing. He explained that they will be doing so once the QS report is out so that they can estimate the remaining work pending.

    Thats all for now.

    Thanks!

  136. 161

    Broken Heart said,

    Thanks to Suresh too…so when they will continue their work?.

  137. 162

    CJ said,

    stop work for 2 weeks? QS evaluation? hehe, i just afraid another top up needed.

  138. 163

    nicky said,

    any 1 can give me contact of FH ?


Comment RSS · TrackBack URI

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.