The Day Has Come // CCF Approved & Issued

Dear fellow purchasers,

It’s with great pleasure to announce that FH have finally received complete support letter from relevant authorities therefore the CCF submission to MPAJ will be on next Monday, 23JUN2014 with target key handover before Hari Raya Puasa.

Regards,

Vincent

 

Comments (58) »

Progress Meeting @ 29AUG2013

Dear all,

Latest photos, credit to Cikgu Rafidah.

imageimageimageimageimage image image image image

Dear all,

Latest photos taken from the site, circular pending finalization from FH.

IMG_2238[1]IMG_2241[1]IMG_2244[1]IMG_2245[1]IMG_2243[1]

Dear fellow purchasers,

NWV

Please find attached progress report further to meeting @ 29AUG2013. FH will share more updates by mid-SEP2013 and they maintained the same timeline as per latest circular.

For more clarification / inquiry, please contact FH team (Kumar, Jason, Yi Wen & Calvin) at 603-22971150.

Regards,

Vincent

Comments (63) »

Progress Meeting @ 29MAY2013 // Circular Posted Out @ 17JUN2013

Latest photos, credit to Casey @ A-10-12

IMG_1803[1] IMG_1802[1] IMG_1801[1] IMG_1800[1] IMG_1799[1] IMG_1798[1] IMG_1797[1] IMG_1796[1] IMG_1795[1] IMG_1794[1] IMG_1793[1] IMG_1791[1] IMG_1790[1] IMG_1789[1] IMG_1788[1] IMG_1787[1] IMG_1786[1] IMG_1784[1] IMG_1783[1] IMG_1782[1] IMG_1781[1] IMG_1780[1] IMG_1779[1] IMG_1778[1] IMG_1777[1] IMG_1776[1] IMG_1775[1] IMG_1774[1]

Latest site photos taken @ 18JUL2013

IMG_1708 IMG_1705 IMG_1707[1] IMG_1706[1] IMG_1704[1]

Latest exterior photos taken @ 07JUL2013

IMG_1685[1] IMG_1686[1] IMG_1687[1]

Dear purchasers

Please note that FH has send out the circular update via post to the last registered address and do expect to receive it within a week. For more clarification / inquiry, please contact FH team (Kumar, Jason, Yi Wen & Calvin) at 603-22971150.

Updated photo from the site.

IMG_1650[1] IMG_1653[1] IMG_1651[1] IMG_1652[1]

Dear fellow purchasers,

Please find the updates as append below.

1) Work Progress as at 29MAY2013-refer attachment below. The delay was mainly due to rectification works require and FH will issue circular to all purchaser on the details, expected by 2nd week of JUN2013

BP

2) Site photo-refer below.

IMG_1568 IMG_1569 IMG_1570 IMG_1571 IMG_1572 IMG_1573 IMG_1574 IMG_1575 IMG_1576 IMG_1577 IMG_1578 IMG_1579 IMG_1580 IMG_1581 IMG_1582 IMG_1583 IMG_1584 IMG_1586 IMG_1587 IMG_1588 IMG_1589

3) Expected completion date: OCT2013.

For more clarification / inquiry, please contact FH team (Kumar, Jason, Yi Wen & Calvin) at 603-22971150.

Regards,
Vincent

Comments (17) »

Construction Progress Meeting, 14MAR2013

Dear all,

We attended the meeting with FH & Conlay Construction on 14MAR2013 and append below are the updates.

Attached progress report for your perusal. FH_14MAR2013

Latest photo @ site: IMG_1505[1]

1) Completion rate is 68.82% which is ahead of schedule rate of 68.02 as at 11MAR2013.

2) Currently there is 208 workers on site working 7 days week to meet the construction deadline.

3) Internal flooring has been completed for Block B while progressing till 8th floor for Block A

4) Lift has been installed for both blocks with test on low speed, once TNB certification complete high speed test will be conduct.

5) Part of the painting work will be done for Block B (subject to weather permitted) while painting for Block A will be done once the exterior plastering work is complete.

6) Master title has been redeemed, pending release from Maybank. FH committed to submit for Strata Title application within 6 – 12 months on VP delivery. Target to receive CF in 2 months time from submission to local council, KPKT is in the loop on the progress of construction and subsequently application for CF, VP & Strata Title.

7) FH has received permit to sell the terminated units and target to begin the selling progress by early APR2013, showroom will be construct to attract buyer. Indicative selling price of MYR 220K onwards. Please contact FH if interested to purchase.

Next meeting will be held in May prior to completion of the construction.

Cheers,

Vincent

Comments (72) »

Site Progress Update @ 30JAN2013

Dear all purchasers,

Please find updates as shared by FH & Conlay, the work progress at site is approximately 45.33% which is 6.08% ahead of schedule. In this regard, please find attached the following documents for your kind attention:-

i. Work Progress Shedule as at 15 January 2013; and

ii. S-Curve of the Project as at 15 January 2013.

S-Curve Work Progress

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Cheers,

Vincent

Comments (25) »

Meeting with FH, Conlay Construction, EA & KPKT

Dear all,

We have the meeting at the project site yesterday and given the progress report as attached. Overall there was close to 100 workers and more to come. The tower crane has been installed and now pending for approved permit. Overall, the progress was convincing and at the moment work was ahead of schedule.

Cheers,

Vincent

Link to progress report: FH CC

photo 4 photo 3 photo 2 photo 1

Comments (25) »

New Contractor Appointed-Conlay Construction Sdn Bhd

Dear fellow purchasers,

Please to update that Conlay Construction Sdn Bhd has taken possession to project site on 1st August 2012 and the completion will take 10 months as stipulated in the contract. As per the meeting earlier, they are self funding until the project completion which by then banks will release the remaining loan sum according to schedule.

FH will sent out the circular accordingly.

Regards,

Vincent

Circular to Purchasers.Conlay Appointment

Comments (45) »

Follow

Get every new post delivered to your Inbox.

Join 30 other followers